Gibraltar Global Cable Barrier System

Case Studies

Alberta, Canada

Contractor: Alberta Highway Services
System: TL4- 4 Cable
Linear Feet: 432,960 ft. / 323 miles of cable
Challenge:

  • The cable barrier was being installed on 80 miles of one of the
    busiest stretches of highway in Canada.
  • The installation required 6 crews to work together:
    • Cable Loading Crew
    • Socket Planting Crew
    • Post Driving Crew
    • Stringing Crew
    • Cable Tensioning Crew
    • Terminal End Crew
  • The timeline for installation was 45 days.

Outcome: The cable barrier was successfully installed in 45 days with no traffic
problems, no collisions and no crew injuries or accidents.